Off-plan project delayed in Dubai: handover date, your rights and compensation
An edited guide in questions and answers by the HomeProof Research Team. Not a live chat.
An edited guide in questions and answers by the HomeProof Research Team. Not a live chat.
Check the project in the Dubai REST app, the DLD's official app.
Go to Services, then Project Status (Mashrooi), then search by project name.
Mashrooi shows the projected completion date, the completion percentage, the last inspection date and site photos. Each project has a status: active, finished or cancelled. A fourth status, "under cancellation", has also been reported.
reviews every project from time to time. It asks the to update the expected completion date and the completion rate. So the date in Mashrooi can be different from the date in your .
A project's technical report expires three months after the last one. If the last inspection date is old, note it.
You can also ask for more proof:
Often the allows some delay.
Many SPAs let the extend the "anticipated completion date" by a further 12 months. Read the extension clause in your own SPA.
Dubai law also lists reasons beyond the developer's control (). Under Article 21 of Executive Council Resolution No. 6 of 2010, these include:
The is the main rule for a delay claim.
Under Article 246(1) of the Civil Transactions Law, a contract must be performed by its terms and in good faith.
These are the main routes in Dubai law:
| Route | What it does | Legal basis |
|---|---|---|
| DLD conciliation | The DLD can help both sides agree. A settlement it approves binds both sides. | Resolution 6/2010, Art. 14 |
| DLD investigation | If the DLD finds a broke the law, the matter is sent for investigation. | Law 13/2008, Art. 13 |
| Court claim | You can ask a court for compensation or to end the contract. | Civil Transactions Law, Art. 295; Resolution 6/2010, Art. 20 |
| Arbitration | Possible only if your SPA has an arbitration clause. | Your SPA |
You keep the right to go to court or arbitration. The DLD complaint form against a real estate company does not handle compensation, money claims or contract disputes.
Sometimes, but not automatically.
Courts look at the facts of each case.
In Case 41/2012, the Dubai Court of Cassation ruled on a late . It held that the buyer could end the contract. The court said the buyer could stop further payments from the day after the handover date.
A 2026 law-firm note says a delay does not automatically allow termination. Courts weigh four things:
Under Article 20 of Resolution 6/2010, a buyer may also ask a court to end the contract in other cases. These include a material change from the agreed specifications, or serious defects that make the unit unfit for use.
In one case reported in February 2026, a delay was more than three years. A Dubai court cut the amount the developer could keep from 40% to 10%. It ordered a refund of Dh185,000 plus 5% interest. That is about ₹47.8 lakh or PKR 1.39 crore.
First, the .
It sets the completion date, the extension clause and compensation. Under Article 295, compensation is what the SPA sets or what a court orders.
To claim in court, you must prove three things:
Court cases in Dubai "can take many months and, on occasions, years", according to UK government guidance last updated in January 2020. Check current court fees with Dubai Courts before you file.
If a project's completion is not above 5%, 's monitoring process applies.
The gets time to correct the situation. If it does not, cancellation procedures start.
A project may then show "under cancellation" in the app. This means RERA is still reviewing whether to cancel it. For what happens after a cancellation, read Off-plan project cancelled in Dubai.
If you want to leave the contract or sell the unit, read Can't pay or want out of an off-plan contract?.
Open the Dubai REST app and go to Project Status (Mashrooi). It shows the projected completion date, the completion percentage and the last inspection date.
RERA asks developers to update the expected completion date, so the date in the register can change. Many SPAs also let the developer extend the completion date by a further 12 months.
Compensation is what your SPA sets or what a Dubai court orders. In court, you must prove the breach, the actual damage and the link between them.
In Case 41/2012, the Dubai Court of Cassation said a buyer could stop payments from the day after the agreed handover date. A 2026 law-firm note says a delay does not automatically allow termination, so courts look at each case.
No. The DLD says it does not have the authority to end a contract between a developer and a buyer. It can help both sides reach a settlement.
This is general information, not legal or financial advice. Rules change; check with a qualified adviser in the UAE, India or Pakistan.