Dubai off-plan project cancelled: how the refund works, step by step

Dubai off-plan project cancelled? Refund rules explained: what RERA cancellation triggers, the 14- and 60-day steps, and what happens if escrow runs short.

By HomeProof Research TeamUpdated 7 min readDubai law · every fact with a source

Short answer

  • When RERA cancels a Dubai project by a final, reasoned decision, the developer must refund all payments made by buyers (Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020).
  • Escrow funds available are refunded within 14 days of cancellation, and the developer must pay any shortfall within 60 days, which RERA can extend (ECR 6/2010, per Al Tamimi).
  • If the developer does not pay, RERA refers the matter to the judicial authorities.
  • Unfinished and cancelled projects can go to the Special Tribunal for Liquidation of Cancelled Real Property Projects, set up by Decree No. 33 of 2020.
  • Recovery depends on what is left in escrow; the DLD describes the liquidation timeline as indefinite.

If your Dubai off-plan project has been cancelled, the refund question has a clear legal answer and a less certain practical one. The law requires a full refund; how much arrives, and when, depends on the money left in the project's escrow account.

Below: what cancellation means, the refund sequence, what happens when escrow is short, and what to prepare, under Dubai law.

Dubai off-plan project cancelled: what refund does the law require?

A RERA cancellation triggers a legal duty to refund everything you paid. Under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, if RERA cancels a project by a final, reasoned decision, the developer "must refund all payments made by the purchasers" under the escrow law.

RERA is the Real Estate Regulatory Agency, the regulatory arm of the Dubai Land Department (DLD). The 2020 amendment matters: under the older text, a developer could keep up to 30% where work had not started. That deduction no longer exists, as Al Tamimi confirmed in 2021.

A project is officially deemed 'cancelled' when Rera issues a final, reasoned decision…
Nikhat Sardar Khan, lawyer, head of corporate, DIFC Litigation and Arbitration at Hilal & Associates · Khaleej Times, Dec 2024

Why can RERA cancel a project?

RERA may cancel a project under Executive Council Resolution No. 6 of 2010 (ECR 6/2010), Article 23, according to Al Tamimi. Grounds include failing to start work without good reason, offences under the escrow law, bankruptcy and no genuine intention to carry out the project.

The DLD's FAQ adds that where a project is not cancelled but completion does not exceed 5%, RERA monitors it, gives the developer time to correct, and starts cancellation if it does not.

Cancelled project in Dubai: what happens to my money, step by step?

The refund follows a sequence set by ECR 6/2010 and summarized by Al Tamimi (2013), with the DLD's FAQ confirming the 60-day step.

Refund sequence after a RERA cancellation

Day 0
RERA issues the cancellation decision
Within 7 working days
Developer may appeal; RERA's rejection is finalECR 6/2010, Art. 24
Within 14 days
Escrow funds available are refunded to buyers; an auditor is appointed at the developer's costArt. 25
Within 60 days
Developer pays any shortfall; RERA can extend thisArt. 26
If unpaid
RERA refers the matter to the judicial authoritiesArt. 27

Escrow is the project's dedicated bank account under Dubai Law No. 8 of 2007. Article 9(1) of that law says deposits in it cannot be seized by the developer's creditors, which is why it sits first in the refund queue.

Refund owed on RERA cancellation
All payments
Source: Law No. 19 of 2020
Escrow refund step
14 days
Source: ECR 6/2010 via Al Tamimi
Shortfall deadline
60 days, extendable
Source: DLD FAQ
Liquidation timeline
Indefinite
Source: DLD FAQ

What if the escrow account doesn't cover the refund?

When escrow runs short, the legal right stays but recovery slows. The developer owes the difference within 60 days; if it does not pay, RERA refers the matter to the courts, and the case may move into liquidation.

Unfinished, cancelled and liquidated projects can go to the Special Tribunal for Liquidation of Cancelled Real Property Projects, created by Decree No. 33 of 2020. It replaced the committee set up by Decree No. 21 of 2013. Its decisions are final and enforced by the Dubai Courts' Execution Court, according to the Dubai Media Office.

The DLD's Real Estate Projects Liquidation Section distributes escrow funds "in full or proportionally" depending on what is available, and its FAQ calls the expected time to liquidate indefinite. The tribunal process is covered in depth in the cancelled-project liquidation guide.

…I have yet to see the funds despite repeatedly pressing the claims…
an investor who won a court verdict, quoted in Gulf News · Gulf News, Sept 2018

What history shows (2008–09 era)

Historical press gives context, not a forecast. Gulf News reported in September 2018 that more than 150 projects, mostly launched from 2005 to 2008, were listed as cancelled in Dubai Courts records. Court cases took about 2 to 4 years, and some investors reportedly recovered only 20 to 30 fils per dirham from escrow.

Those projects predate the 2020 amendment.

How do you confirm a project is cancelled and claim your refund?

Confirm the status in official records, then assemble proof of every payment. The Dubai REST app shows a status label for each registered project; Gulf News (2023) reported that labels show whether a project is active, finished or cancelled.

  1. Check the official status

    In the DLD's Dubai REST app, open Project Status (Mashrooi) and search by project name. Note the status, escrow account details and completion percentage.
  2. Gather your proof

    Collect the SPA, the Oqood certificate (your interim registration), every receipt and bank confirmation, and the account each payment went into.
  3. Ask for your records

    Under Article 12 of Law No. 8 of 2007, depositors may see their own accounting records with the escrow agent and ask for copies.
  4. Take advice on filing

    Ask a UAE-qualified lawyer whether your claim goes to liquidation, the tribunal or the courts, and what documents each needs.

Payments made outside escrow are harder to trace in a liquidation. Our guide to verifying an escrow account explains how to confirm where past payments went.

Off plan project cancelled in the UAE: does Dubai's rule apply everywhere?

No. Dubai's refund rules come from Dubai laws. Each emirate has its own property regulator and rules, and Abu Dhabi has a separate framework under its Law No. 3 of 2015, amended by Law No. 2 of 2025.

Before you rely on any refund figure, confirm which emirate's register the project sits in. If a cancellation turns into a contest with the developer, see handling an off-plan dispute. Checking takes minutes; you can see the official project status before your next step.

Buying from the UK, US, Canada or Australia?

Do I get a full refund if RERA cancels my project?
A buyer is legally owed a full refund when RERA cancels a Dubai project by a final, reasoned decision, under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020. How much is actually recovered, and when, depends on what remains in the project's escrow account and on the developer paying any shortfall.
How long does a RERA cancelled project refund take?
A RERA cancelled project refund starts with escrow funds, which ECR 6/2010 says are refunded within 14 days of cancellation. The developer then has 60 days, extendable by RERA, to pay any shortfall. If a project moves into liquidation, the DLD describes the timeline as indefinite.
Can the developer keep 30% if work never started?
A Dubai developer can no longer keep 30% when work never started. Law No. 19 of 2020 removed that deduction: if work has not started for reasons beyond the developer's control, or RERA cancels the project, all payments must be refunded. Older articles citing 30% describe the previous text.
What happens to my money in a cancelled Dubai project if escrow is empty?
If a cancelled Dubai project's escrow account is short, the developer must pay the shortfall within 60 days, extendable by RERA, or RERA refers the matter to the courts. In liquidation, funds are distributed in full or proportionally. Hadef & Partners noted buyers may then rank as unsecured creditors.

Sources

  1. Law No. 19 of 2020 amending Law No. 13 of 2008 (Dubai Legislation Portal)
  2. Law No. 8 of 2007 concerning escrow accounts (Dubai Legislation Portal)
  3. Special judicial committee to handle Dubai's cancelled real estate projects (Al Tamimi)
  4. Frequently asked questions (Dubai Land Department)
  5. Mohammed bin Rashid issues new legislations (Dubai Media Office, December 2020)
  6. Had Dubai escrow law succeeded in securing purchasers' money? (Hadef & Partners)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Second opinion, before or after you buy

A check takes minutes. Not checking can cost everything.

HomeProof checks a UAE project and its developer against up to 80 parameters from government registries and open sources. We sell no property and take no commission, so you see the facts and make the call yourself.