Check construction progress on off-plan Dubai property before each payment: a routine for US buyers

Check construction progress on off-plan Dubai property before payment: a US buyer's routine for completion %, escrow details and dates before every wire.

By HomeProof Research TeamUpdated 5 min readDubai law · every fact with a source

Short answer

  • To check construction progress on off-plan Dubai property before payment, US buyers can open the project in the Dubai REST app's Project Status (Mashrooi) service, which the DLD says shows the completion percentage, site photos and the escrow account number.
  • The DLD FAQ says payments follow completion rates, and an investor can ask for a letter from the DLD-approved project consultant confirming current completion before paying.
  • An independent completion report from RERA's technical auditor costs AED 15,000 per unit, about $4,084.

Treat each installment request as a checkpoint.

How to check construction progress off-plan in Dubai before payment, for US buyers

Open the project in Dubai REST, compare the completion percentage with the milestone in your payment plan, confirm the escrow account number, and only then wire.

  1. Read the payment request

    Note the milestone it cites.
  2. Open Project Status

    Completion %, dates, photos.
  3. Compare with the SPA

    Does the milestone match?
  4. Ask for proof if needed

    Consultant letter or auditor report.
  5. Wire to escrow only

    Confirm the account number first.

Step 1: Read what the payment request is tied to

Your SPA (sale and purchase agreement) sets the payment plan; some installments follow dates, others milestones. Note which milestone this request relies on.

Step 2: Check the Dubai REST project status and completion percentage from the US

The DLD's Dubai REST page says off-plan investors can see project details including the completion percentage, actual project photos and the escrow account number. The DLD's guide to Project Status (Mashrooi) adds developer details and inspection details.

Gulf News reported in 2023 that the app also shows the projected completion date, the last inspection date with a report, and whether the project is active, finished or canceled.

Step 3: Compare the figures with your contract

If the request says a milestone is reached, the completion percentage should support it. The DLD FAQ says payments follow completion rates. Payment plans are set by each SPA, so read your own clause.

…stop paying the installment because the developer has stopped building?
a buyer who had paid 60 per cent, writing to Gulf News' Ask the Law · Gulf News, Oct 2023

Completion also matters if you stop paying. Under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, the share a Dubai developer may keep after a buyer default depends on the whole project's completion.

Most a Dubai developer may keep after buyer default, by whole-project completion

Values in % of unit value

25%
Below 60% (work started)
40%
60% to 80%
40%
Above 80%one of three options for the developer
Source: Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020

If construction has not started for reasons outside the developer's control, or RERA cancels the project, the same article requires a full refund. If the numbers and the request disagree, see our dispute route map.

Step 4: Ask for written proof when the numbers do not match

The DLD FAQ says an investor can ask for a letter from the DLD-approved project consultant confirming the current completion percentage before paying a developer's request. For a fully independent figure, RERA's technical auditor will produce a completion report for AED 15,000 per unit, about $4,084 at the AED 3.6725 peg.

Check the date on the figure you are shown. The DLD FAQ says RERA periodically asks developers to update the completion rate and expected completion date, and charges a technical report fee where the report is more than three months old.

Step 5: Wire only to the project escrow account

The DLD FAQ says all amounts received from off-plan buyers go into the project escrow account. Confirm the number in Dubai REST against the invoice; our escrow verification playbook explains how.

Plan the timing. Dubai is 8 hours ahead of New York and 11 ahead of Los Angeles until November 1, 2026, then 9 and 12, so ask your questions in the evening and wire after the reply. If money already went elsewhere, read paid outside escrow. For the wider picture, see the global guide to construction checks and the overview for American buyers, or check the project's registry facts now.

Before the next installment: questions from American buyers

Should I pay the next installment on my off-plan property, as an American buyer?
Whether to pay the next off-plan installment is your decision, but check first. The DLD FAQ says payments follow completion rates and that you can ask for the project consultant's completion letter before paying. Compare the Dubai REST completion percentage with the milestone in your SPA, and confirm the escrow account number before you wire.
Can I see the Dubai REST project status and completion percentage from the US?
The Dubai REST app shows project status and completion percentage to off-plan investors, according to the DLD. From the US, the App Store notes say foreign investors log in with UAE PASS or a title deed. Most off-plan buyers have no deed yet, so UAE PASS, which has a Visitor path, is the practical route.
How much does an independent completion report cost in Dubai?
The DLD FAQ says an investor can obtain a completion report from RERA's technical auditor for AED 15,000 per unit or villa, roughly $4,084 at the AED 3.6725 dollar peg. It gives a completion figure that does not come from the developer.
Can my US bank reverse an installment wired to Dubai?
A US bank cannot simply reverse an international wire. The CFPB says remittance transfers over $15 can be canceled within 30 minutes unless the money has been deposited. After that, a recall is a request that needs the receiving bank's cooperation. Regulation E's protections exclude wire transfer systems such as Fedwire.

Sources

  1. Dubai REST (Dubai Land Department)
  2. Project Status (Mashrooi) user guide (DLD)
  3. DLD frequently asked questions
  4. Dubai Law No. 19 of 2020 amending Law No. 13 of 2008
  5. What is a remittance transfer? (CFPB)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Already bought off-plan?

Know where your project stands before every payment.

Track your off-plan instalments, and run a Property Check whenever you want the project's registry facts. HomeProof shows facts; what you do with them is your decision.

  • Installment Plan for your payment schedule
  • Property Checks against government registries
  • No commission from developers or brokers
Check a project