Off-plan termination at 25% or 40% in Dubai: the Article 11 tiers for buyers in Canada

Off plan termination 25% 40% Dubai rules from Canada: the Article 11 tiers under Law 19 of 2020, worked in round numbers, with the DLD notice timeline.

By HomeProof Research TeamUpdated 6 min readDubai law · every fact with a source

Short answer

  • The rules are in Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, issued 24 November 2020 and still the version in force.
  • Below 60% completion of the whole project, with work started: the developer may terminate and keep up to 25% of the unit value.
  • From 60% to 80%: up to 40%. Above 80%: keep the contract and claim the balance, ask the DLD to auction the unit, or terminate and keep up to 40%.
  • Work not started for reasons beyond the developer's control, or a project cancelled by RERA: all payments must be refunded.
  • Any excess is refunded within one year of termination or 60 days of resale, whichever is earlier.

Off-plan termination at 25% or 40% in Dubai is a rule buyers in Canada often hear about second-hand, often in an outdated form. The current text is Law No. 19 of 2020, and two details change the arithmetic: percentages apply to the unit value in the contract, and completion is measured on the whole project.

The Article 11 sequence after a buyer defaults

Step 1
Developer notifies the DLD of the default on the DLD form
Step 2
DLD serves a dated written notice: 30 days to performIn person, registered mail, email or another approved method
During the 30 days
DLD may mediate; any settlement becomes a signed SPA addendum
Day 31+
DLD issues a document stating the project's completion percentage
Then
Developer may use the option allowed for that tier

How do the 25% and 40% off-plan termination tiers work for buyers in Canada?

The tier depends on how far the whole project is built, as certified by the DLD under RERA standards. The single unit's progress does not decide it.

Maximum share of unit value a developer may keep

0%
Not started / RERA-cancelledfull refund
25%
Below 60%, work started
40%
60% to 80%
40%
Above 80%, if terminatingother options also available
Source: Law No. 19 of 2020 (Dubai Legislation Portal)
Notice period
30 days
Source: Law No. 19 of 2020
Basis
Unit value in the contract
Source: Law No. 19 of 2020
Excess refund
1 year or 60 days after resale
whichever is earlier
Source: Law No. 19 of 2020
Court access
Preserved
Art. 11(g)
Source: Law No. 19 of 2020

What does Article 11 of Law 13 of 2008 mean in numbers?

Run the tiers on round, hypothetical figures before reading any developer letter. The cap is a share of the unit value, not of what you paid, so it can exceed your payments.

Example: a hypothetical AED 1,000,000 unit
Project completionPaid so farDeveloper may keep up toExcess refundable
50% (work started)AED 400,000AED 250,000AED 150,000
70%AED 500,000AED 400,000AED 100,000
Not startedAED 100,000NothingAED 100,000

Example figures only. In Canadian terms, run the same steps on what you actually sent in CAD, then use the AED amounts on your receipts, since the law works in the contract currency.

is it fair the developer keeps all the money?
an off-plan property owner quoted in Gulf News · Gulf News, Jan 2021

What changed with Law 19 of 2020 for Dubai off-plan buyers in Canada?

Two things matter most, according to Al Tamimi (March 2021): a full refund where work has not started, where previously up to 30% could be kept, and completion measured on the whole project instead of the unit.

Article 11(f) treats these rules as public order, so acts that ignore them are null.

What should you check before accepting a termination figure?

Check that the process was followed and the tier is right. The DLD FAQ notes that an investor can ask for a letter from the DLD-approved project consultant confirming the completion percentage before paying a developer's request.

Verifying a termination claim

What should buyers in Canada do around the notice period?

Treat the 30 days as short, given an 8- to 11-hour gap. Dubai is UTC+4 all year; Toronto is 8 hours behind until 1 November 2026, then 9, and Vancouver, on permanent Pacific time since March 2026, is 11 hours behind all year.

If money comes back, ask a Canadian tax adviser how it affects reporting; the CRA's T1135 applies where specified foreign property costs more than $100,000. This is general information only.

See also what follows a missed instalment, all exits compared, the global tiers guide and the Canadian buyers' hub. You can also see the project's registry completion data.

Is the 25% or 40% based on what I paid or on the property price?
The 25% or 40% under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, is a share of the unit value stated in the contract, not of the amount paid. A Dubai developer keeps up to that cap and must refund any excess within the deadlines the law sets.
Does the 60% threshold refer to my unit or the whole building?
The 60% threshold in Dubai's Article 11 refers to the whole project. Law No. 19 of 2020 says the DLD states the completion percentage of the real property project, calculated under RERA standards. Al Tamimi confirms the 2020 change from unit-level to project-level measurement.
Can a Dubai developer still keep 30% if construction never started?
No. Under Law No. 19 of 2020, if work has not started for reasons beyond the developer's control and without its negligence, or RERA cancels the project, the developer must refund all payments. The 30% deduction for unstarted projects belonged to earlier versions of Article 11.
Can buyers in Canada challenge a termination in court?
Yes. Article 11(g), as amended by Law No. 19 of 2020, says the termination rules do not prevent a buyer from going to court or arbitration. Buyers in Canada usually act through a UAE-qualified lawyer, often found through the list of local lawyers that Canadian consular officials provide.

Sources

  1. Law No. 19 of 2020 amending Law No. 13 of 2008 (Dubai Legislation Portal)
  2. Dubai amends interim registration law (Al Tamimi, March 2021)
  3. Law No. 13 of 2008 regulating the Interim Property Register (Dubai Legislation Portal)
  4. Frequently asked questions (Dubai Land Department)
  5. Questions and answers about Form T1135 (Canada Revenue Agency)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Second opinion, before or after you buy

A check takes minutes. Not checking can cost everything.

HomeProof checks a UAE project and its developer against up to 80 parameters from government registries and open sources. We sell no property and take no commission, so you see the facts and make the call yourself.

  • Registration, escrow and completion data in one place
  • Developer delivery track record from open data
  • No broker, no commission, no verdict
Check a project